Sewage Treatment Plant, Baquedano Locality

Client: Bhp Billinton, Minera Spence
Delivery Date: April 2014
Location: Antofagasta, Chile

•Extension and automation of existing Plant from 1 l/s to 20 l/s
•Two reactors of 200 m3 of capacity were built and one of the same capacity was technologically upgraded.
•Supply of equipment needed for the project
•Installation of the equipment
•Installation of interconnecting piping
•Installation of electricity
•Installation of automation and control system
•Construction added a qualitative leap in the standards of quality of treated water, as well as strong technological development.

Project under FAST TRACK mode


Engineering Phases:
  • Prefeasibility
  • Feasibility
  • Desing
  • Procurement
  • Construction & Installation
  • Pre-comissioning
  • Comissioning
  • Start-up
  • Operation Service
  • Maintenance Service
  • Transfer

 