•This is an EPC project that included basic engineering and includes testing and commissioning and subsequent operation and transfer.
•The treatment plant is an activated sludge plant.
•The average flow is 11m3/hr.
•Design made with high standards of energy efficiency and minimal environmental impact, according to the current policies of CODELCO.
•The PTAS built by Eathisa is part of converting the open pit mine to underground mine